Hull Final Inspection for Eurodam

Krazy Kruizers

Holland America Specialist







Captain’s Log: Eurodam’s Final Hull Inspection

Captain Bowland | April 12th, 2011
The paint job on the underside of the ship is complete. The team has carried out the final inspection and the dock will be filled with water later this evening to the 5 meter mark. The ship will still be sitting on the blocks but it allows us to bring the ships systems on line. At this point all shore side service connections will be disconnected. Tomorrow morning we will float the ship. Next is the interior, pics to follow.



 